Capex for India’s green energy transmission lines to double to Rs 1 lakh crore in next 2 fiscals

During the construction phase, transmission projects face multiple execution risks, including right of way (ROW), forest clearances, and supply chain issues. Nevertheless, credit profiles of developers remain supported by healthy cash flows and strong funding visibility, the report stated.

An analysis of three developers, estimated to account for 80-85 per cent of the expected capex, indicates as much.

Strengthening the transmission infrastructure is critical given the momentum in renewable capacity addition. Crisil Ratings expects addition of 65-75 GW of solar and wind capacities over fiscals 2026 and 2027. Timely planning and commissioning of transmission capacities remains critical as the execution period of a transmission project is typically 2-4 years — twice that of a renewable energy project.

“Considering the need for transmission capacity augmentation, project awarding ramped up to Rs 1.6 lakh crore in fiscals 2024 and 2025,” said Manish Gupta of Crisil Ratings.

“We have seen these projects incurring an average delay of about 10 months in commissioning, with few projects even seeing delays of over 18 months. Factoring these delays, we estimate transmission connectivity to be enabled for up to 60 GW of potential renewable capacity by fiscal 2027,” he explained.

To support faster execution, the Ministry of Power has amended the land compensation guidelines for ROW for transmission projects. For instance, in June 2024, land compensation for tower base area for high-voltage transmission lines was increased to 200 per cent from 85 per cent of land value, increasing the compensation for landowners and, thereby, reduce ROW-induced delays.

Moreover, considering the urgent ramp-up required in the transmission sector, maintaining an uninterrupted supply chain, especially for sub-station equipment like transformers as well as high-voltage direct current (HVDC) components will remain critical for timely execution.

Anand Kulkarni, Director, Crisil Ratings, said that “we expect these projects to generate return on equity of 11-14 per cent”.

Notwithstanding the sensitivity of returns to project delays, developers are well placed to absorb the rising capex intensity.

“Equity requirements are well supported by recent fund raises aggregating to around Rs. 12,500 crore through equity capital markets and players’ estimated free cash flows of around Rs. 30,000 crore over the next two fiscals from their existing operational portfolio, Kulkarni explained. (IANS)

Latest News

DIFFERENCE the leaders can make : MJ Akbar

The limits of ideology-II AS I write, 45 years after...

Tackling landlessness

2.69 crore houses built for rural poor AS many as...

Unesco recognition for four MP historical sites

FOUR historical heritage sites of Madhya Pradesh — Ashokan...

Indigo MD meets Fadnavis

MUMBAI: Indigo Airlines Managing Director Rahul Bhatia had a meeting...

Honour for Kanger Park

CHHATTISGARH’S Kanger Valley National Park has been included in...

Topics

DIFFERENCE the leaders can make : MJ Akbar

The limits of ideology-II AS I write, 45 years after...

Tackling landlessness

2.69 crore houses built for rural poor AS many as...

Unesco recognition for four MP historical sites

FOUR historical heritage sites of Madhya Pradesh — Ashokan...

Indigo MD meets Fadnavis

MUMBAI: Indigo Airlines Managing Director Rahul Bhatia had a meeting...

Honour for Kanger Park

CHHATTISGARH’S Kanger Valley National Park has been included in...

India emerging as global leader in Web3 sector

INDIA is fast emerging as a global leader in...

COP30 President cites limits of global climate summits

AFTER decades of United Nations climate summits, the model...

New Zealand PM to be on four-day visit to INDIA

PRIME Minister of New Zealand, Christopher Luxon, will pay...
spot_img

Related Articles

Popular Categories

spot_imgspot_img