Capex for India’s green energy transmission lines to double to Rs 1 lakh crore in next 2 fiscals

During the construction phase, transmission projects face multiple execution risks, including right of way (ROW), forest clearances, and supply chain issues. Nevertheless, credit profiles of developers remain supported by healthy cash flows and strong funding visibility, the report stated.

An analysis of three developers, estimated to account for 80-85 per cent of the expected capex, indicates as much.

Strengthening the transmission infrastructure is critical given the momentum in renewable capacity addition. Crisil Ratings expects addition of 65-75 GW of solar and wind capacities over fiscals 2026 and 2027. Timely planning and commissioning of transmission capacities remains critical as the execution period of a transmission project is typically 2-4 years — twice that of a renewable energy project.

“Considering the need for transmission capacity augmentation, project awarding ramped up to Rs 1.6 lakh crore in fiscals 2024 and 2025,” said Manish Gupta of Crisil Ratings.

“We have seen these projects incurring an average delay of about 10 months in commissioning, with few projects even seeing delays of over 18 months. Factoring these delays, we estimate transmission connectivity to be enabled for up to 60 GW of potential renewable capacity by fiscal 2027,” he explained.

To support faster execution, the Ministry of Power has amended the land compensation guidelines for ROW for transmission projects. For instance, in June 2024, land compensation for tower base area for high-voltage transmission lines was increased to 200 per cent from 85 per cent of land value, increasing the compensation for landowners and, thereby, reduce ROW-induced delays.

Moreover, considering the urgent ramp-up required in the transmission sector, maintaining an uninterrupted supply chain, especially for sub-station equipment like transformers as well as high-voltage direct current (HVDC) components will remain critical for timely execution.

Anand Kulkarni, Director, Crisil Ratings, said that “we expect these projects to generate return on equity of 11-14 per cent”.

Notwithstanding the sensitivity of returns to project delays, developers are well placed to absorb the rising capex intensity.

“Equity requirements are well supported by recent fund raises aggregating to around Rs. 12,500 crore through equity capital markets and players’ estimated free cash flows of around Rs. 30,000 crore over the next two fiscals from their existing operational portfolio, Kulkarni explained. (IANS)

Latest News

When SUN becomes son, & starts paying: Urban poor are now producing power through solar rooftop and selling it too

ANOOP SAXENA NEW DELHI: In the labyrinthine lanes of Dharavi,...

The largest blue-collar employer

Blitz Bureau NEW DELHI: Who maintains the millions of rooftop...

The Solar DIY guide

Blitz Bureau NEW DELHI: Thinking of going solar this summer?...

Quality over quantity

Blitz Bureau NEW DELHI: The Fiscal Health Index 2026 puts...

A CHINA TALE: What makes the country an economic wonder

Shalini S Sharma NEW DELHI: Shanghai is the third most...

Topics

The largest blue-collar employer

Blitz Bureau NEW DELHI: Who maintains the millions of rooftop...

The Solar DIY guide

Blitz Bureau NEW DELHI: Thinking of going solar this summer?...

Quality over quantity

Blitz Bureau NEW DELHI: The Fiscal Health Index 2026 puts...

A CHINA TALE: What makes the country an economic wonder

Shalini S Sharma NEW DELHI: Shanghai is the third most...

Oil efforts on war footing

Blitz Bureau NEW DELHI: In light of the evolving situation...

Let’s not overestimate resilience from oil shocks

Deepak Dwivedi NEW DELHI: India must read Donald Trump’s latest...
spot_img